Six horses graze on a derelict patch of land in Middlesbrough, a symbol of England's enduring failure to construct enough homes. Once earmarked for 2,400 homes in 2004, the site has seen only 216 built over two decades, with promised funding never materializing.

This stagnation in Middlesbrough, alongside similar projects in York and the Isle of Sheppey in Kent, highlights the complex reasons behind the UK's housing crisis, where demand consistently outstrips supply. Combined, the three sites visited by BBC News were intended to deliver 7,400 homes, but only 326 have been completed.

"When our larger sites get a bit stuck, that has a disproportionate impact on national housebuilding," explains Anthony Breach, director of policy and research at the Centre for Cities think tank. He notes the UK's reliance on large, complex schemes, which become problematic when delayed.

In Middlesbrough, the Middlehaven scheme, initially envisioned as a £500m development including homes, a theatre, and restaurants, faced financial shortfalls from its inception. A revised plan in 2013, which involved demolishing 185 existing homes, has resulted in a net gain of only 31 homes.

The economic impact of events like the 2008 financial crash has significantly curtailed progress. In Middlesbrough, the crash led to the departure of the council's development partner. While a college campus and business spaces have been built, the housing component has lagged.

Breach emphasizes that the price of new homes is crucial for developers' returns. In areas with lower house prices, public funds may be necessary to bridge the gap between building costs and sale prices. Middlesbrough Council has recently announced plans for 462 homes on the site, aiming for a total of 3,400, but acknowledges the funding challenges.

York Central, a plan for 3,000 homes announced in 2001, has yet to see a single house built. Planning consultant Nora Galley, who developed the masterplan, points to a lack of capacity in the UK's construction industry to manage such large-scale projects, citing supply chain issues and a shortage of skilled workers. The Construction Industry Training Board estimates a need for 206,000 new construction workers by 2030. The York Central project's cost has ballooned to £2bn.

On the Isle of Sheppey, a 23-year-old plan for up to 2,000 homes, initially promoted as a £400m regeneration, has yielded only 110 houses. The projected investment figure, according to Swale Borough Council, was an estimate, and no housing developer was initially secured. A retail park has been built, but the marina plans were scrapped, leaving fields intended for housing.

These delays have significant consequences, with local councils reporting long waiting lists for social housing and missed opportunities for economic growth. The issue is not unique to these three locations; other large projects, such as Convoy's Wharf in London, have also faced prolonged delays.

However, there are some signs of progress. Barking Riverside in London, after years of stalled development due to poor transport links, has seen 3,000 homes built since the creation of a new rail line, with plans for further expansion. Mayoral development corporations are also being established to streamline planning processes for large projects.

The Ministry of Housing reports an increase in housing starts and efforts to unblock stalled schemes. Despite these initiatives, the persistent challenges in delivering housing at scale, as exemplified by the stalled sites in Middlesbrough, York, and Kent, underscore the deep-rooted issues contributing to England's housing shortage.